PJM-AH2-335
130 MW storage in York, PA · In queue since March 2022 · Proposed COD December 2025
130 MW
Capacity
1
Components
Battery
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 9m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
PJM-AH2-335 is a proposed 130 MW battery storage project located in York County, Pennsylvania. The project, which consists entirely of battery storage, entered the PJM interconnection queue on March 10, 2022, with a proposed commercial operation date of December 31, 2025.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The point of interconnection is Roundtop 115 kV. The Market Entity (ME) is the listed utility.
Generated from interconnection queue and public data sources
State
PA
County
York
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ME
Entity
PJM
Service Type
—
Point of Interconnection
Roundtop 115 kV
Data Source
LBNL + Live
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ROUNDTOP115 KV 1B71
- POI Substation
- Roundtop Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PJM-AH2-335Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.