PJM-AH1-722
158.1 MW generation in Union, NJ · In queue since April 2025 · Proposed COD May 2030
158.1 MW
Capacity
1
Components
Gas
1y 7m
In Queue
System Impact Study
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 1m
Study Phase
TC2
Interconnection request submitted to ISO/RTO
Active; Phase 3; TC2
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-05-31
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 23, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Project entered PJM interconnection queue
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: No COD provided in LBNL queue snapshot and no news or search results available to establish a target date.
Developer: Only LBNL filing entity available. No news or search results to determine if this is a shell LLC or identify a parent company.
Status: LBNL status shows active queue position with System Impact Study in progress. No contradictory information available.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
PJM-AH1-722 is a proposed natural gas-fired generation project in Union County, New Jersey, with a total capacity of 158.1 megawatts (MW). The development project is sponsored by Parkway Generation Operating LLC and would interconnect with the transmission system of PSEG at the Linden 230 kV point of interconnection. The project consists of a single gas generation component, and its request is for Network Resource Interconnection Service (NRIS).
The project entered the PJM Interconnection queue on April 8, 2025, and holds an active status. It is in the System Impact Study stage of the interconnection process and is being evaluated in PJM's Transition Cycle 2 (TC2) study phase. The proposed commercial operation date is May 31, 2030.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM_CYCLE queue source as of: Oct 23, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NJ
County
Union
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Parkway Generation Operating LLC
Utility
PSEG
Entity
PJM
Service Type
NRIS
Point of Interconnection
Linden 230kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- BETHESDA34 KV BETHTRIA
- POI Substation
- Linden Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.