PJM-AH1-704
24 MW generation in Monroe, OH · In queue since April 2025 · Proposed COD January 2026
24 MW
Capacity
1
Components
Gas
1y 7m
In Queue
System Impact Study
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
9 months
Schedule
10 months past proposed COD
Study Phase
TC2
Interconnection request submitted to ISO/RTO
Active; Phase 3; TC2
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-01-31
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
PJM-AH1-704 is a proposed 24 MW natural gas generation project in Monroe County, Ohio, developed by Long Ridge Energy Generation LLC. The development project would interconnect within the PJM Interconnection region at the Hannibal 138 kV point of interconnection, in the service territory of the utility AEP. The project consists of a single gas-fired component and has requested Network Resource Interconnection Service (NRIS).
The project entered the PJM interconnection queue on April 3, 2025, and its queue status is active. It is being evaluated in PJM's Transition Cycle 2 (TC2) study phase, with its interconnection agreement status listed at the System Impact Study stage. The proposed commercial operation date is January 31, 2026. The project has appeared in one recent news article, categorized as regulatory coverage.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM_CYCLE queue source as of: Oct 23, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OH
County
Monroe
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Long Ridge Energy Generation LLC
Utility
AEP
Entity
PJM
Service Type
NRIS
Point of Interconnection
Hannibal 138 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.