PJM-AH1-580
200 MW generation in Harrison, OH · In queue since March 2025 · Proposed COD December 2029
200 MW
Capacity
1
Components
Solar
1y 8m
In Queue
System Impact Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 9m
Study Phase
TC2
Interconnection request submitted to ISO/RTO
Active; Phase 3; TC2
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 23, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Entered PJM queue for System Impact Study
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available showing proposed COD of May 2025. No independent sources to verify or contradict this date, which appears optimistic given the project is still in System Impact Study phase as of March 2025.
Developer: Only LBNL filing entity available. No research found to identify parent company or operating entity behind this project LLC.
Status: LBNL shows active queue status in early interconnection study phase. No news or public announcements found to indicate project progression beyond this stage.
About
Generated Apr 10, 2026 · Predates Oct 23, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The proposed project PJM-AH1-580 is a 200 MW solar generation project located in Harrison County, Ohio. The project is interconnected to the PJM Interconnection queue, with an entry date of September 10, 2021, and a proposed commercial operation date of May 1, 2025. The interconnecting utility is AEP, and the point of interconnection is the Nottingham Switch 138 kV. The interconnection agreement status is listed as "In Progress (unknown study)".
The development project consists of 200 MW of solar photovoltaic generation. It is currently listed as an active project within the PJM queue.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM_CYCLE queue source as of: Oct 23, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OH
County
Harrison
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Energy Pastures Solar Project, LLC
Utility
AEP
Entity
PJM
Service Type
NRIS
Point of Interconnection
Nottingham 138 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- 02CPP_NH138 KV TR2
- POI Substation
- Nottingham Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PJM-AH1-580Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.