Project PJM-AH1-260 — Project Summary

Queue ID
PJM-AH1-260
Capacity
300 MW
Technology
Battery
Status
active
Location
Camden, NJ
Region
PJM
Developer
Haddy Energy Storage LLC
IA Status
System Impact Study

PJM-AH1-260

PJM-AH1-260BetaActiveBatteryPJMLBNL + Live

300 MW storage in Camden, NJ · In queue since January 2025 · Proposed COD December 2029

BA: PJMISO/RTO: PJMNERC: RFCRC: PJM

300 MW

Capacity

1

Components

Battery

1y 10m

In Queue

System Impact Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 11m

Study Phase

TC2

Impact Study25%
Queue EntryJan 27, 2025

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

Active; Phase 3; TC2

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-12-01

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Dec 1, 2029
From queue filing
Developer in saved assessment
Haddy Energy Storage LLC
From queue filing
Status at research time
Active
Active in PJM queue (AH1-260), System Impact Study stage, no IA executed. No external evidence of construction or permitting.
Financing
Not recorded
Research sources and reasoning (0 recorded sources)

low confidence at research time

No source list recorded with this assessment.

Commercial operation date: Only the LBNL snapshot provides a date (proposed_cod 2029-12-01). No news or live search findings were available to confirm or contradict it.

Developer: Only the LBNL filing entity is available. No press releases or search results identify a parent or operating company behind this LLC.

Status: LBNL lists status as active with a System Impact Study underway and an ia_date of null. No other sources contradict this.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 23, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

PJM-AH1-260 is a proposed 300 MW battery storage project located in Camden County, New Jersey. The project, which consists entirely of battery storage, is being developed within the PJM Interconnection queue. Its queue entry date is September 10, 2021, with a proposed commercial operation date of June 30, 2025. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)".

The project's point of interconnection (POI) is the New Freedom 230 kV substation. The interconnecting utility is PSEG.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • PJM_CYCLE queue source as of: Oct 23, 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

NJ

County

Camden

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Haddy Energy Storage LLC

Utility

AEC

Entity

PJM

Service Type

NRIS

Point of Interconnection

New Freedom - Monroe 230 kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
PJM
Trading Hub
WESTERN HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.