Poseidon Solar 1
40 MW generation in Fayette, PA · In queue since February 2025 · Proposed COD December 2024
40 MW
Capacity
1
Components
Solar
1y 3m
In Queue
System Impact Study
IA Phase
COD target: 2024
Total Duration
1y 3m
Schedule
17 months past proposed COD
Study Phase
TC2
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
PJM-AH1-247 is a proposed solar generation project with a total capacity of 40 MW, located in Fayette County, Pennsylvania. The project is in the PJM interconnection queue, with an entry date of September 9, 2021, and a proposed commercial operation date of December 31, 2024. The interconnecting utility is APS.
The project's interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
PA
County
Fayette
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Poseidon Energy, LLC
Utility
APS
Entity
PJM
Service Type
NRIS
Point of Interconnection
Lardin - Lake Lynn 138kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Poseidon Solar 1Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.