PJM-AH1-151
200 MW generation in Lee, IL · In queue since August 2021 · Proposed COD December 2025
200 MW
Capacity
1
Components
Solar
4y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
4y 4m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
PJM-AH1-151 is a proposed solar generation project with a total capacity of 200 MW. The project is located in Lee County, Illinois, within the ComEd service area and the PJM Interconnection region. The project, which entered the PJM queue on August 27, 2021, has a proposed commercial operation date of December 31, 2025.
The interconnection agreement for PJM-AH1-151 is currently listed as "In Progress (unknown study)". The point of interconnection is the Nelson-Electric Junction 345 kV line. The project is listed as "active" in the interconnection queue.
Generated from interconnection queue and public data sources
State
IL
County
Lee
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Nelson-Electric Junction 345 kV
Data Source
LBNL
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PJM-AH1-151Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.