Evergreen Energy Center
20 MW storage in Loudoun, VA · In queue since February 2025 · Proposed COD December 2022
20 MW
Capacity
1
Components
Battery
1y 3m
In Queue
System Impact Study
IA Phase
COD target: 2022
Total Duration
1y 3m
Schedule
42 months past proposed COD
Study Phase
TC2
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-23
PJM-AH1-125 is a proposed 20 MW battery storage project located in Loudoun County, Virginia. The project is interconnected within the PJM Interconnection queue, having entered the queue on August 23, 2021. Dominion is the listed utility. The proposed commercial operation date is December 23, 2022, and the interconnection agreement status is listed as "In Progress (unknown study)".
The development project consists solely of battery storage, with a total capacity of 20 MW. The point of interconnection is the Sycoline 34.5kV line.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
VA
County
Loudoun
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Evergreen Energy Center, LLC
Utility
Dominion
Entity
PJM
Service Type
ERIS
Point of Interconnection
Sycoline 34.5kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Evergreen Energy CenterForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.