PJM-AH1-092
90 MW hybrid in Halifax, VA · In queue since July 2021 · Proposed COD June 2025
90 MW
Capacity
1
Components
Solar
4y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 11m
Schedule
12 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-01
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
PJM-AH1-092 is a proposed 90 MW hybrid solar and battery project located in Halifax County, Virginia. The project, which consists of 90 MW of solar capacity, is in the PJM interconnection queue, with an entry date of July 30, 2021. The proposed commercial operation date is June 1, 2025. Dominion is the interconnecting utility.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the SedgeHill - Person 230 kV line. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
VA
County
Halifax
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
SedgeHill - Person 230 kV
Data Source
LBNL
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PJM-AH1-092Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.