Crossroads Solar I
20 MW generation in Morrow, OH · In queue since April 2025 · Proposed COD December 2024
20 MW
Capacity
1
Components
Solar
1y 1m
In Queue
System Impact Study
IA Phase
COD target: 2024
Total Duration
1y 1m
Schedule
17 months past proposed COD
Study Phase
TC2
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
PJM-AH1-060 is a proposed solar generation project with a total capacity of 20 MW. The project is located in Morrow County, Ohio, within the PJM Interconnection region and is being managed by utility ATSI. The project entered the PJM queue on July 20, 2021, with a proposed commercial operation date of December 31, 2024.
The interconnection agreement for PJM-AH1-060 is currently listed as "In Progress (unknown study)". The point of interconnection is the Cardington-Liberty 69 kV III substation. The project has appeared in recent news coverage regarding renewable energy development in the PJM region.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OH
County
Morrow
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Crossroads Solar I, LLC
Utility
ATSI
Entity
PJM
Service Type
NRIS
Point of Interconnection
Cardington-Liberty 69 kV III
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Crossroads Solar IForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.