PJM-AH1-055
220 MW generation in Jackson, OH · In queue since February 2025 · Proposed COD November 2026
220 MW
Capacity
1
Components
Solar
1y 5m
In Queue
System Impact Study
IA Phase
COD target: 2026
Total Duration
1y 9m
Study Phase
TC2
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-11-15
Project entered PJM queue for System Impact Study
PJM-AH1-055 is a proposed 220 MW solar generation project located in Jackson County, Ohio. The project is listed in the PJM interconnection queue as of July 14, 2021, with a proposed commercial operation date of November 15, 2026. The interconnection customer is OVEC.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Kyger Creek - Don Marquis 345 kV line.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OH
County
Jackson
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Furnace Solar, LLC
Utility
OVEC
Entity
PJM
Service Type
NRIS
Point of Interconnection
Kyger Creek - Don Marquis 345 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MARQUIS
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.