PJM-AH1-044
200 MW generation in Lee, IL · In queue since February 2025 · Proposed COD October 2029
200 MW
Capacity
1
Components
Solar
1y 9m
In Queue
System Impact Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 8m
Study Phase
TC2
Interconnection request submitted to ISO/RTO
Active; Phase 3; TC2
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-10-31
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 23, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Entered PJM queue for System Impact Study
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of 2024-12-31. No independent sources to verify or update this date, which is now in the past while project remains in System Impact Study phase.
Developer: Only LBNL filing entity available. No research findings to identify parent company or operating entity behind the project LLC.
Status: LBNL shows active queue status in System Impact Study. Proposed COD of Dec 2024 has passed, suggesting timeline delays typical of early-stage interconnection projects.
About
Generated Apr 10, 2026 · Predates Oct 23, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
PJM-AH1-044 is a proposed solar generation project with a total capacity of 200 MW, located in Lee County, Illinois. The project is interconnected within the PJM Interconnection queue, having entered the queue on June 30, 2021. The developer is unknown. The proposed commercial operation date is December 31, 2024.
The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Nelson - Electric Junction 345 kV line. The project is within the ComEd utility territory.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM_CYCLE queue source as of: Oct 23, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Lee
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Steward Creek Solar, LLC
Utility
ComEd
Entity
PJM
Service Type
NRIS
Point of Interconnection
Nelson - Electric Junction 345 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- HIGH
- POI Substation
- Nelson TS
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Illinois Solar in Illinois growth signals — PPAs, construction, new projects
Summary analysis with parallel narrative sections and visualizations.
OE IL Solar 3
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
OE IL Solar 3
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Steward Creek Solar
Data-driven briefing on Steward Creek Solar — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.