PJM-AG2-516
120 MW generation in Winnebago, IL · In queue since February 2025 · Proposed COD October 2023
120 MW
Capacity
1
Components
Solar
1y 5m
In Queue
System Impact Study
IA Phase
COD target: 2023
Total Duration
1y 5m
Schedule
33 months past proposed COD
Study Phase
TC2
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-10-31
Original proposed COD per LBNL queue filing (now past)
PJM-AG2-516 is a proposed solar generation project located in Winnebago County, Illinois, within the PJM Interconnection region. The project, with a total capacity of 120 MW, consists entirely of solar photovoltaic generation. Its point of interconnection is at the Pecatonica 138kV substation.
The project entered the PJM interconnection queue on March 31, 2021, with a proposed commercial operation date of October 31, 2023. As of the latest data, the project's interconnection agreement status is listed as "In Progress (unknown study)". The utility involved in the interconnection is ComEd.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Winnebago
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Kestrel Solar, LLC
Utility
ComEd
Entity
PJM
Service Type
NRIS
Point of Interconnection
Pecatonica 138kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PJM-AG2-516Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.