PJM-AG2-411
63 MW generation in Somerset, PA · In queue since March 2025 · Proposed COD December 2028
63 MW
Capacity
1
Components
Solar
1y 8m
In Queue
System Impact Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 9m
Study Phase
TC2
Interconnection request submitted to ISO/RTO
Active; Phase 3; TC2
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
About
Generated Apr 10, 2026 · Predates Oct 23, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
PJM-AG2-411 is a proposed 63 MW solar generation project located in Somerset County, Pennsylvania. The project is interconnected within the PJM Interconnection queue, with an initial queue entry date of March 31, 2021. The proposed commercial operation date is July 1, 2024.
The interconnection agreement for PJM-AG2-411 is currently listed as "In Progress (unknown study)". The point of interconnection is the Statler Hill 115 kV substation. The project is within the PENELEC utility territory.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM_CYCLE queue source as of: Oct 23, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
PA
County
Somerset
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Iris Energy LLC
Utility
PENELEC
Entity
PJM
Service Type
NRIS
Point of Interconnection
Statler Hill 115 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- STATHILL34.5 KV FORWRDWF
- POI Substation
- Statler Hill Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.