PJM-AG2-382
70 MW generation in Bertie, NC · In queue since February 2025 · Proposed COD September 2024
70 MW
Capacity
1
Components
Solar
1y 5m
In Queue
System Impact Study
IA Phase
COD target: 2024
Total Duration
1y 5m
Schedule
22 months past proposed COD
Study Phase
TC2
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-20
PJM-AG2-382 is a proposed 70 MW solar generation project located in Bertie County, North Carolina. The project is in the PJM interconnection queue, having entered on March 29, 2021, with a proposed commercial operation date of September 20, 2024. Dominion is listed as the utility.
The interconnection agreement for PJM-AG2-382 is currently listed as "In Progress (unknown study)". The point of interconnection is the Cashie 230 kV substation.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NC
County
Bertie
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Merry Hill PV I, LLC
Utility
Dominion
Entity
PJM
Service Type
NRIS
Point of Interconnection
Cashie 230 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CASHIE 35 KV TX1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PJM-AG2-382Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.