PJM-AG2-364
200 MW generation in Tazewell, IL · In queue since March 2025 · Proposed COD December 2028
200 MW
Capacity
1
Components
Solar
1y 8m
In Queue
System Impact Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 9m
Study Phase
TC2
Interconnection request submitted to ISO/RTO
Active; Phase 3; TC2
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 23, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Original proposed commercial operation date per LBNL queue filing
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available showing proposed COD of 2024-05-31. This date is already past and project is still in System Impact Study phase, indicating the date is stale but no alternative sources exist to establish a revised target.
Developer: Only LBNL filing entity 'Mackinaw Solar LLC' is available. No research findings to determine if this is a project-specific LLC or identify a parent operating company.
Status: LBNL shows 'active' status with project in System Impact Study phase. The proposed 2024-05-31 COD has already passed, suggesting timeline delays but no withdrawal or suspension.
About
Generated Apr 10, 2026 · Predates Oct 23, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
PJM-AG2-364 is a proposed 200 MW solar generation project located in Tazewell County, Illinois. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 26, 2021. Its proposed commercial operation date is May 31, 2024.
The interconnection agreement for the project with utility ComEd is currently listed as "In Progress (unknown study)". The point of interconnection is the Powerton 345 kV substation. The developer is not specified in the queue data.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM_CYCLE queue source as of: Oct 23, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Tazewell
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Mackinaw Solar LLC
Utility
ComEd
Entity
PJM
Service Type
NRIS
Point of Interconnection
Powerton 345 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- 3 POWERT24 KV PO-5
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Illinois Solar in Illinois growth signals — PPAs, construction, new projects
Summary analysis with parallel narrative sections and visualizations.
OE IL Solar 3
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
OE IL Solar 3
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.