PJM-AG2-297
19 MW generation in Cumberland, NJ · In queue since March 2021 · Proposed COD June 2023
19 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 3m
Schedule
36 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-06-01
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
PJM-AG2-297 is a proposed solar generation project located in Cumberland County, New Jersey, within the PJM Interconnection region. The development project, with a total capacity of 19 MW, consists entirely of solar photovoltaic generation. The project was entered into the PJM interconnection queue on March 23, 2021, with a proposed commercial operation date of June 1, 2023. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
The proposed project is being developed within the Atlantic Electric Company (AEC) service area and connects to the Cumberland 230 kV point of interconnection. The project is currently listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
NJ
County
Cumberland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEC
Entity
PJM
Service Type
—
Point of Interconnection
Cumberland 230 kV
Data Source
LBNL
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CUMB APS138 KV T9
- POI Substation
- Cumberland Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PJM-AG2-297Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.