PJM-AG2-272
55 MW storage in Pittsylvania, VA · In queue since February 2025 · Proposed COD October 2024
55 MW
Capacity
1
Components
Battery
1y 5m
In Queue
System Impact Study
IA Phase
COD target: 2024
Total Duration
1y 5m
Schedule
22 months past proposed COD
Study Phase
TC2
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-01
PJM-AG2-272 is a proposed 55 MW battery storage project located in Pittsylvania County, Virginia. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 19, 2021. The developer is unknown. The proposed commercial operation date is October 1, 2024.
The interconnection agreement for PJM-AG2-272 is currently listed as "In Progress (unknown study)". The point of interconnection is the Berry Hill 138 kV substation. The project is within the service territory of utility AEP.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
VA
County
Pittsylvania
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Tupelo Storage, LLC
Utility
AEP
Entity
PJM
Service Type
NRIS
Point of Interconnection
Berry Hill 138 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PJM-AG2-272Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.