PJM-AG2-200
17 MW generation in Warren, PA · In queue since February 2025 · Proposed COD January 2023
17 MW
Capacity
1
Components
Solar
1y 5m
In Queue
System Impact Study
IA Phase
COD target: 2023
Total Duration
1y 5m
Schedule
42 months past proposed COD
Study Phase
TC2
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-01-15
The proposed project PJM-AG2-200 is a 20 MW solar generation project located in Warren County, Pennsylvania. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 2, 2021, with a proposed commercial operation date of January 15, 2023. The project's interconnection agreement status is listed as "In Progress (unknown study)".
The proposed project is located within the PENELEC utility service area. The point of interconnection is the North Warren_x0013_Russell 34.5 kV location.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
PA
County
Warren
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Sugaree Solar LLC
Utility
PENELEC
Entity
PJM
Service Type
NRIS
Point of Interconnection
North Warren - Russell 34.5 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PJM-AG2-200Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.