PJM-AG2-114
100 MW generation in Livingston, IL · In queue since February 2025 · Proposed COD March 2024
100 MW
Capacity
1
Components
Solar
1y 5m
In Queue
System Impact Study
IA Phase
COD target: 2024
Total Duration
1y 5m
Schedule
29 months past proposed COD
Study Phase
TC2
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-03-01
Original proposed commercial operation date per LBNL queue filing
PJM-AG2-114 is a proposed solar generation project with a total capacity of 100 MW, located in Livingston County, Illinois. The project is in the PJM interconnection queue, having entered on January 29, 2021, with a proposed commercial operation date of March 1, 2024. The interconnecting utility is ComEd, and the point of interconnection is the Dresden-Pontiac Midpoint 345 kV line. The interconnection agreement status is listed as "In Progress (unknown study)".
The development project consists of 100 MW of solar photovoltaic generation. It is currently listed as an active project within the PJM queue. The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Livingston
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
CPV Prairie Dock Solar, LLC
Utility
ComEd
Entity
PJM
Service Type
NRIS
Point of Interconnection
Dresden-Pontiac Midpoint 345 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PJM-AG2-114Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.