PJM-AG2-082
200 MW generation in Harrison, OH · In queue since March 2025 · Proposed COD December 2029
200 MW
Capacity
1
Components
Solar
1y 8m
In Queue
System Impact Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 9m
Study Phase
TC2
Interconnection request submitted to ISO/RTO
Active; Phase 3; TC2
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 23, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Original proposed commercial operation date per LBNL queue filing
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available showing proposed COD of December 2024. No independent sources to verify or contradict this date, though it appears already past and project is still in System Impact Study phase.
Developer: Only LBNL filing entity available. Name structure suggests project-specific LLC, but no research findings identify parent company or operating entity.
Status: LBNL shows Active status in System Impact Study. Proposed COD of Dec 2024 is now past (queue date is March 2025), suggesting timeline has slipped but project remains in queue.
About
Generated Apr 10, 2026 · Predates Oct 23, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
PJM-AG2-082 is a proposed 200 MW solar generation project located in Harrison County, Ohio. The project is in the PJM interconnection queue, having entered on January 22, 2021, with a proposed commercial operation date of December 1, 2024. The interconnection agreement is currently listed as "In Progress (unknown study)". The interconnecting utility is AEP.
The development project consists of 200 MW of solar photovoltaic generation. The point of interconnection is the Nottingham 138 kV substation.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM_CYCLE queue source as of: Oct 23, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OH
County
Harrison
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Energy Pastures Solar Project, LLC
Utility
AEP
Entity
PJM
Service Type
NRIS
Point of Interconnection
Nottingham 138 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- 02CPP_NH138 KV TR2
- POI Substation
- Nottingham Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.