PJM-AG2-069
150 MW generation in Brunswick, VA · In queue since February 2025 · Proposed COD December 2029
150 MW
Capacity
1
Components
Solar
1y 9m
In Queue
System Impact Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 10m
Study Phase
TC2
Interconnection request submitted to ISO/RTO
Active; Phase 3; TC2
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 23, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Project entered PJM interconnection queue AG2-069
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of December 2025. No independent news or research sources to validate or contradict this date.
Developer: LBNL lists 'Virginia Electric and Power Company' which is the legal utility name for Dominion Energy Virginia, the operating brand of Dominion Energy's regulated utility subsidiary in Virginia.
Status: LBNL status shows active queue position in System Impact Study phase. This is a utility-owned generation project by Dominion Energy, recently entered into PJM queue in February 2025.
About
Generated Apr 10, 2026 · Predates Oct 23, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
PJM-AG2-069 is a proposed solar generation project with a total capacity of 150 MW. The project is located in Brunswick County, Virginia, and is being developed within the Dominion service area. It is interconnected within the PJM Interconnection queue, with an entry date of December 30, 2020. The proposed commercial operation date is December 1, 2025.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Heritage-Wake 500 kV substation.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM_CYCLE queue source as of: Oct 23, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
VA
County
Brunswick
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Virginia Electric and Power Company
Utility
Dominion
Entity
PJM
Service Type
NRIS
Point of Interconnection
Heritage - Wake 500 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.