Fourth Quarter
500 MW storage in Montgomery, MD · In queue since October 2020 · Proposed COD February 2030
500 MW
Capacity
1
Components
Battery
6y 1m
In Queue
IA Executed
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
9y 4m
Study Phase
TC1
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
EP; FINAL AGREEMENT; TC1
Project under construction
Typical: 6–18 months
Proposed COD: 2030-02-01
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
PJM awarded interconnection agreements to 23 BESS resources (2.2 GW); news extraction links this project to the approved batch.
energy-storage.newsThe 300 MW Fourth Quarter BESS withdrew from Maryland's first-round storage procurement. This is not a PJM queue withdrawal.
pv-magazine-usa.comResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- americas.rwe.com/our-energy/storage/storage-projects-and-locations/fourth-quarter-bess/
- psc.maryland.gov/news/2026/maryland-public-service-commission-announces-first-round-energy-storage-awards/
- pv-magazine-usa.com/2026/10/08/marylands-first-storage-procurement-round-falls-360-mw-short/
- energy-storage.news/pjm-awards-interconnection-agreements-to-23-bess-resources/
Commercial operation date: No post-LBNL source gives a COD for the project. The RWE project page and Maryland PSC coverage describe it but state no operation date, so the LBNL proposed COD of 2030-02-01 stands unverified.
Developer: RWE's Americas site hosts a project page titled 'Fourth Quarter BESS strengthens Maryland grid', so the LBNL project LLC appears to be RWE's vehicle. The page snippet doesn't spell out the ownership relationship, so this is an inference.
Status: LBNL shows IA Executed/active, and Energy-Storage.News (Dec 2025) covers PJM's first batch of BESS IAs. The Maryland procurement withdrawal is a separate offtake/support program, not a queue withdrawal.
About
Generated Apr 10, 2026 · Predates Oct 23, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Fourth Quarter project is a proposed 500 MW battery storage project located in Montgomery County, Maryland. Interconnecting to PEPCO via the Dickerson 230 kV point of interconnection, the project is in the PJM interconnection queue as entry AG1-483, with a queue entry date of October 1, 2020. The proposed commercial operation date is June 1, 2024. As of the current interconnection status, the project is in the System Impact Study phase.
The Fourth Quarter project has been the subject of recent news coverage, with 30 articles published on the project. The news coverage primarily focuses on industry developments, with additional articles covering deals, grid infrastructure, and project development.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM_CYCLE queue source as of: Oct 23, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MD
County
Montgomery
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Fourth Quarter BESS, LLC
Utility
PEPCO
Entity
PJM
Service Type
NRIS
Point of Interconnection
Dickerson 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- DICKERSH13 KV HCT1
- POI Substation
- Dickerson H Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14
View all articlesBattery Storage queue pipeline by status
Data tables and metrics from the InfraSure database.
Battery storage queue pipeline
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
MD - CS - BGE - PR24 TPE
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.