Barrelhead (PJM-AG1-471) — Project Summary

Queue ID
PJM-AG1-471
Capacity
54 MW
Technology
Solar
Status
active
Location
KY
Region
PJM
Developer
Barrelhead Solar, LLC
IA Status
IA Executed

Barrelhead

PJM-AG1-471BetaActiveSolarPJMLBNL

54 MW generation in KY · In queue since September 2020 · Proposed COD January 2029

BA: PJMISO/RTO: PJMNERC: SERCRC: MISO

54 MW

Capacity

1

Components

Solar

5y 8m

In Queue

IA Executed

IA Phase

COD target: 2029

Interconnection

Total Duration

8y 4m

Study Phase

TC1

Construction75%
Queue EntrySep 30, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2029-01-15

About

PJM-AG1-471 is a proposed solar generation project with a total capacity of 54 MW. The project is located in Kentucky and is being developed within the PJM Interconnection queue. The queue entry date is September 30, 2020, with a proposed commercial operation date of October 2, 2023. The project's interconnection status is currently in the System Impact Study phase. The designated point of interconnection is the Up Church-Wayne County 69 kV line.

The project is sponsored by EKPC and consists solely of solar photovoltaic generation, with the entire 54 MW capacity attributed to solar. The project is listed as active within the PJM queue.

Generated from interconnection queue and public data sources

Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

KY

County

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Barrelhead Solar, LLC

Utility

EKPC

Entity

PJM

Service Type

NRIS

Point of Interconnection

Up Church-Wayne County 69 kV

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
PJM
Trading Hub
AEP-DAYTON HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No Ask reports yet for this entity.

Ask about Barrelhead
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.