Black Diamond Solar
30 MW storage in Christian, IL · In queue since September 2020 · Proposed COD June 2022
30 MW
Capacity
1
Components
Battery
5y 8m
In Queue
System Impact Study
IA Phase
COD target: 2022
Total Duration
1y 9m
Schedule
49 months past proposed COD
Study Phase
TC1
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-06-01
PJM-AG1-460 is a proposed 30 MW battery storage project located in Christian County, Illinois. The project is interconnected within the PJM Interconnection queue, having entered the queue on September 30, 2020. The proposed commercial operation date is June 1, 2022. The project's interconnection status is currently in the System Impact Study phase.
The development project consists solely of battery storage, with a total capacity of 30 MW. The interconnecting utility is ComEd, and the point of interconnection (POI) is the Kincaid-Pana 345 kV line.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Christian
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Black Diamond Solar Power, LLC
Utility
ComEd
Entity
PJM
Service Type
NRIS
Point of Interconnection
Kincaid-Pana 345 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Black Diamond SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.