PJM-AG1-435
150 MW generation in Bureau, IL · In queue since September 2020 · Proposed COD December 2023
150 MW
Capacity
1
Components
Wind
5y 8m
In Queue
Feasibility Study
IA Status
COD target: 2023
Total Duration
3y 3m
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
PJM-AG1-435 is a proposed wind generation project with a total capacity of 150 MW. The project is located in Bureau County, Illinois, and is interconnected within the PJM Interconnection region, served by the utility ComEd. The project entered the PJM queue on September 30, 2020, with a proposed commercial operation date of December 31, 2023.
The project's interconnection status is currently in the Feasibility Study phase. The point of interconnection (POI) is the Kewanee-Hennepin 138 kV line.
Generated from interconnection queue and public data sources
State
IL
County
Bureau
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Kewanee-Hennepin 138 kV
Data Source
LBNL
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PJM-AG1-435Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.