Prairie Creek Wind Phase 2
100 MW generation in Blackford, IN · In queue since September 2020 · Proposed COD May 2029
100 MW
Capacity
1
Components
Wind
6y 2m
In Queue
IA Executed
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8y 8m
Study Phase
TC1
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
UC; FINAL AGREEMENT; TC1
Project under construction
Typical: 18–36 months
Proposed COD: 2029-05-31
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 23, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed per PJM queue status
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of May 2029. No independent news or press releases found to validate or contradict this target date.
Developer: Only LBNL filing entity available. No press releases or corporate announcements found to identify a parent operating company distinct from the project LLC.
Status: LBNL reports Interconnection Agreement executed with active queue status. No news coverage found to provide ground-truth updates on project progression beyond queue position.
About
Generated Apr 10, 2026 · Predates Oct 23, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
PJM-AG1-433 is a proposed 100 MW wind generation project located in Blackford County, Indiana. The project, which consists of 100 MW of wind capacity, is in the PJM interconnection queue as of September 30, 2020, with a proposed commercial operation date of December 31, 2023. The interconnecting utility is AEP. Its interconnection status is currently in the Feasibility Study phase.
The point of interconnection for PJM-AG1-433 is the Keystone-DeSoto 345 kV line. The project is listed in the PJM queue under queue ID AG1-433.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM_CYCLE queue source as of: Oct 23, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IN
County
Blackford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Prairie Creek Wind Farm II, LLC
Utility
AEP
Entity
PJM
Service Type
NRIS
Point of Interconnection
Keystone-DeSoto 345 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Prairie
Data-driven briefing on Prairie — fleet, generation, financial, and news signals.
Prairie Creek FL
Data-driven briefing on Prairie Creek — fleet, generation, financial, and news signals.
Prairie Creek Wind Phase 2
Data-driven briefing on Prairie Creek Wind Phase 2 — fleet, generation, financial, and news signals.
Prairie Creek
Data-driven briefing on Prairie Creek — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.