Dawson Solar
300 MW generation in Mclean, IL · In queue since September 2020 · Proposed COD February 2030
300 MW
Capacity
1
Components
Solar
6y 2m
In Queue
Feasibility Study
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
9y 5m
Study Phase
TC1
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-02-28
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 23, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Entered PJM queue AG1-374 for feasibility study
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of December 2024. No independent news sources found to verify or update this target date.
Developer: LBNL filing entity 'Deriva Energy Solar, LLC' is a project-specific LLC. Parent operating company is Deriva Energy, a renewable energy developer.
Status: LBNL shows Active status in Feasibility Study phase. No news coverage found to indicate project advancement, withdrawal, or construction activity.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Dawson Solar is a proposed 300 MW solar generation project located in McLean County, Illinois. The development project is being pursued by Deriva Energy Solar, LLC and is planned to interconnect within the ComEd utility territory at the Blue Mound 345 kV point of interconnection. The project consists of a single solar component with a capacity of 300 MW and has requested Network Resource Interconnection Service (NRIS).
The project is listed in the PJM Interconnection queue under queue ID PJM-AG1-374, having entered the queue on September 30, 2020. It is participating in PJM's Transition Cycle 1 (TC1) study phase, and its interconnection agreement status is recorded as Feasibility Study. The project's current queue status is listed as suspended. Its proposed commercial operation date is February 28, 2030.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM_CYCLE queue source as of: Oct 23, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Mclean
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Deriva Energy Solar, LLC
Utility
ComEd
Entity
PJM
Service Type
NRIS
Point of Interconnection
Blue Mound 345 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- 989 TWIN34.5 KV HTRAILWF
- POI Substation
- Blue Mound Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Illinois Solar in Illinois growth signals — PPAs, construction, new projects
Summary analysis with parallel narrative sections and visualizations.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
OE IL Solar 3
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
OE IL Solar 3
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.