Jade Meadow III Solar Facility (PJM-AG1-363) — Project Summary

Queue ID
PJM-AG1-363
Capacity
300 MW
Technology
Solar+Battery
Status
active
Location
Garrett, MD
Region
PJM
Developer
—
IA Status
IA Executed

Jade Meadow III Solar Facility

PJM-AG1-363BetaActiveSolarBatteryPJMLBNL + Live

300 MW hybrid in Garrett, MD · In queue since September 2020 · Proposed COD March 2029

BA: PJMISO/RTO: PJMNERC: RFCRC: PJM

300 MW

Capacity

1

Components

Solar

6y 2m

In Queue

IA Executed

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

8y 6m

Construction75%
Queue EntrySep 30, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Engineering and Procurement

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2029-03-31

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
2028
Differs from queue: Mar 31, 2029
Developer in saved assessment
REV Renewables
Filed as Jade Meadow III LLC
Status at research time
Active
Active — IA executed per LBNL; CPCN case 9769 before the Maryland PSC; construction expected to begin in 2026 with COD in 2H 2028
Financing
Not recorded

Milestones in this assessment

COD target2028Latest in this assessment

Developer targets commercial operations in the second half of 2028.

revrenewables.com
Research sources and reasoning (4 recorded sources)

medium confidence at research time

  1. revrenewables.com/jade-meadow-iii/
  2. cleanview.co/power-projects/developers/rev-renewables
  3. interconnection.fyi/project/pjm-ag1-363
  4. interconnection.fyi/projects/transmission-owner/allegheny-power

Commercial operation date: REV Renewables' project page states the project is "expected to begin construction in 2026, and reach commercial operations in the second half of 2028," versus the LBNL proposed COD of 2029-03-31. Only one developer source gives the date, so the year is used without a specific day.

Developer: LBNL developer field is null. The REV Renewables project page and Cleanview's REV developer pipeline list Jade Meadow III, and the Maryland PSC CPCN case (No. 9769) names the applicant as Jade Meadow III LLC, a project LLC.

Status: LBNL lists the project as active with an executed IA, and interconnection trackers show it as active. The REV page confirms continued development, with construction not yet started.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 25, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The proposed Jade Meadow III Solar Facility is a 300 MW hybrid solar and battery energy storage project located in Garrett County, Maryland. The project consists of 300 MW of solar generation capacity. It is listed in the PJM interconnection queue as project AG1-363, with a queue entry date of September 30, 2020, and a proposed commercial operation date of March 31, 2028. The interconnecting utility is APS, and the point of interconnection is the Black Oak-Hatfield 500 kV line.

The project's interconnection agreement has been executed. The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • PJM queue source as of: Oct 25, 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

MD

County

Garrett

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

—

Utility

APS

Entity

PJM

Service Type

NRIS

Point of Interconnection

Black Oak-Hatfield 500 kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
PJM
Trading Hub
WESTERN HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.