Summer Shade Solar
106 MW hybrid in Metcalfe, KY · In queue since September 2020 · Proposed COD December 2028
106 MW
Capacity
1
Components
Solar
6y 2m
In Queue
IA Executed
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8y 3m
Study Phase
TC1
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
EP; FINAL AGREEMENT; TC1
Project under construction
Typical: 18–30 months
Proposed COD: 2028-12-31
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 23, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed per LBNL queue status
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of 2028-12-31. No independent news or press releases found to validate or update this target date.
Developer: Only LBNL filing entity 'Summer Shade Solar, LLC' is available. No news coverage found to identify parent company or operating entity behind this project-specific LLC.
Status: LBNL shows 'active' status with IA Executed, indicating interconnection agreement is in place. However, absence of news coverage suggests project has not yet reached construction or financing milestones.
About
Generated Apr 10, 2026 · Predates Oct 23, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
PJM-AG1-341 is a proposed 106 MW hybrid solar and battery project located in Metcalfe County, Kentucky. The project, which consists of 106 MW of solar generation, is in the PJM interconnection queue, with queue entry date of September 30, 2020. The proposed commercial operation date is June 15, 2023. The interconnecting utility is EKPC.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Summer Shade 161 kV substation. The project has appeared in recent news.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM_CYCLE queue source as of: Oct 23, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
KY
County
Metcalfe
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Summer Shade Solar, LLC
Utility
EKPC
Entity
PJM
Service Type
NRIS
Point of Interconnection
Summer Shade 161 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- EIGHTY8 34.5 KV GLOVERSP
- POI Substation
- Summer Shade Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Summer Shade SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.