Boyles Run Solar
15.9 MW generation in Northumberland, PA · In queue since September 2020 · Proposed COD April 2028
15.9 MW
Capacity
1
Components
Solar
5y 10m
In Queue
IA Executed
IA Phase
COD target: 2028
Total Duration
7y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-04-30
The Boyles Run Solar project is a proposed 15.9 MW solar generation facility in Northumberland County, Pennsylvania. The project is located within the PJM Interconnection region and is linked to the existing BAI-Boyles Run-Phase I operating plant (EIA ID 67954).
The project, identified as queue ID PJM-AG1-260, entered the PJM interconnection queue on September 28, 2020, with a proposed commercial operation date of April 30, 2028. The interconnection agreement has been executed. The designated point of interconnection is the Sunbury-Dalmatia 69 kV line, and the interconnecting utility is PPL.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
PA
County
Northumberland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PPL
Entity
PJM
Service Type
NRIS
Point of Interconnection
Sunbury-Dalmatia 69 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
- POI Substation
- Hunter Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Boyles Run SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.