Dolphin Solar
450 MW generation in Fountain, IN · In queue since September 2020 · Proposed COD June 2024
450 MW
Capacity
1
Components
Solar
5y 8m
In Queue
Feasibility Study
IA Phase
COD target: 2024
Total Duration
3y 9m
Schedule
24 months past proposed COD
Study Phase
TC1
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-01
The proposed PJM-AG1-226 project is a 450 MW solar generation facility located in Fountain County, Indiana. The project, which is in the PJM interconnection queue, was entered on September 24, 2020, with a proposed commercial operation date of June 1, 2024. The interconnecting utility is AEP.
The project's interconnection status is currently in the Feasibility Study phase. The point of interconnection is the Eugene-Dequine 345 kV line. The development project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IN
County
Fountain
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Dolphin Solar LLC
Utility
AEP
Entity
PJM
Service Type
NRIS
Point of Interconnection
Dequine-Eugene 345 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top 10 solar states
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.