Morgan Street-Cochranton 34.5 kV
15 MW generation in Crawford, PA · In queue since September 2020 · Proposed COD March 2026
15 MW
Capacity
1
Components
Solar
5y 10m
In Queue
IA Executed
IA Phase
COD target: 2026
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2026-03-31
The Morgan Street-Cochranton 34.5 kV project is a proposed 15 MW solar generation project located in Crawford County, Pennsylvania. The project is interconnected within the PJM Interconnection queue as project AG1-197, with a queue entry date of September 19, 2020. The proposed commercial operation date is March 31, 2026.
The project's interconnection status is currently in the System Impact Study phase, but is listed as suspended. The proposed point of interconnection is the Morgan Street-Cochranton 34.5 kV substation, within the PENELEC utility territory. The developer is not specified in the available data.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
PA
County
Crawford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
NRIS
Point of Interconnection
Morgan Street-Cochranton 34.5 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Morgan Street-Cochranton 34.5 kVForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.