Southern Ocean Waretown Solar
12 MW generation in Ocean, NJ · In queue since September 2020 · Proposed COD December 2028
12 MW
Capacity
1
Components
Solar
5y 10m
In Queue
IA Executed
IA Phase
COD target: 2028
Total Duration
8y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-12-31
The Southern Ocean Waretown Solar project is a proposed 12 MW solar generation project located in Ocean County, New Jersey. The project is in the PJM interconnection queue as entry AG1-189, with a queue entry date of September 17, 2020, and a proposed commercial operation date of December 31, 2028. The interconnecting utility is JCPL. The project's interconnection agreement has been executed.
The proposed project consists of 12 MW of solar photovoltaic generation. It is located at the Oyster Creek-Bamber Lake 34.5 kV point of interconnection. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NJ
County
Ocean
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
JCPL
Entity
PJM
Service Type
NRIS
Point of Interconnection
Oyster Creek-Bamber Lake 34.5
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Southern Ocean Waretown SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.