Brunswick Battery Storage
75 MW storage in Brunswick, VA · In queue since September 2020 · Proposed COD July 2031
75 MW
Capacity
1
Components
Battery
5y 8m
In Queue
IA Pending
IA Phase
COD target: 2031
Total Duration
10y 10m
Study Phase
TC1
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-07-28
PJM-AG1-153 is a proposed 75 MW battery storage project located in Brunswick County, Virginia. The project is in the PJM interconnection queue, having entered on September 10, 2020. Dominion is the interconnecting utility. The proposed commercial operation date is December 1, 2023.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Heritage 500 kV substation.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
VA
County
Brunswick
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
Utility
Dominion
Entity
PJM
Service Type
NRIS
Point of Interconnection
Heritage 500 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- WMEDINA 138 KV NEM1FEOH
- POI Substation
- Heritage Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Brunswick Battery StorageForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.