Moon Corner Solar
60 MW generation in Richmond, VA · In queue since September 2020 · Proposed COD March 2031
60 MW
Capacity
1
Components
Solar
6y 1m
In Queue
IA Pending
IA Phase
COD target: 2031
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
10y 6m
Study Phase
TC1
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-03-01
PJM-AG1-135 is a proposed solar generation project located in Richmond County, Virginia, within the PJM Interconnection region. The development project, with a total capacity of 60 MW, is being proposed by Dominion. It consists of a single 60 MW solar component.
The project entered the PJM interconnection queue on September 3, 2020, with a proposed commercial operation date of December 1, 2024. Its interconnection status is currently in the System Impact Study phase, and the point of interconnection is the Garner-Lancaster 115 kV line.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
VA
County
Richmond
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
Utility
Dominion
Entity
PJM
Service Type
NRIS
Point of Interconnection
Garner-Lancaster 115 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Dominion-20230829006
Data-driven briefing on Dominion Energy — fleet, generation, financial, and news signals.
Dominion-20230829005
Data-driven briefing on Dominion Energy — fleet, generation, financial, and news signals.
Dominion-20211118005
Data-driven briefing on Dominion Energy — fleet, generation, financial, and news signals.
Dominion-20240829014
Data-driven briefing on Dominion Energy — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.