Red Maple Solar
95.1 MW generation in Dekalb, IL · In queue since August 2020 · Proposed COD May 2028
95.1 MW
Capacity
1
Components
Solar
6y 3m
In Queue
Feasibility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
7y 9m
Study Phase
TC1
Interconnection request submitted to ISO/RTO
EP; FINAL AGREEMENT; TC1
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-31
About
Generated Apr 10, 2026 · Predates Oct 23, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
PJM-AG1-127 is a proposed solar generation project with a total capacity of 95.1 MW, located in Dekalb County, Illinois. The project is in the PJM interconnection queue, having entered the queue on August 31, 2020, with a proposed commercial operation date of December 29, 2023. The interconnection status is currently in the Feasibility Study phase.
The project is located within the ComEd service territory.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM_CYCLE queue source as of: Oct 23, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Dekalb
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Red Maple Solar, LLC
Utility
ComEd
Entity
PJM
Service Type
NRIS
Point of Interconnection
Crego Rd 138 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- H452 138 KV TR1 LD
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Illinois Solar in Illinois growth signals — PPAs, construction, new projects
Summary analysis with parallel narrative sections and visualizations.
Red Maple Solar
Data-driven briefing on Red Maple Solar — fleet, generation, financial, and news signals.
OE IL Solar 3
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
OE IL Solar 3
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.