PJM-AG1-124
90 MW generation in Nelson, VA · In queue since August 2020 · Proposed COD December 2024
90 MW
Capacity
1
Components
Solar
5y 9m
In Queue
System Impact Study
IA Status
COD target: 2024
Total Duration
4y 4m
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-01
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
PJM-AG1-124 is a proposed 90 MW solar generation project located in Nelson County, Virginia. The project is interconnected within the PJM Interconnection queue, having entered the queue on August 31, 2020. The proposed commercial operation date is December 1, 2024. The interconnection request is currently in the System Impact Study phase.
The project, which is being developed within the AEP service territory, consists of 90 MW of solar photovoltaic generation. The point of interconnection is the Gladstone 138 kV substation. The project is currently listed as active within the PJM interconnection queue.
Generated from interconnection queue and public data sources
State
VA
County
Nelson
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Gladstone 138 kV
Data Source
LBNL
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- 02CLINTN138 KV TR71
- POI Substation
- Gladstone Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PJM-AG1-124Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.