Black Moshannon Solar
95 MW hybrid in Centre, PA · In queue since August 2020 · Proposed COD August 2023
95 MW
Capacity
1
Components
Solar
5y 9m
In Queue
IA Executed
IA Phase
COD target: 2023
Total Duration
3 years
Schedule
34 months past proposed COD
Study Phase
TC1
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2023-08-01
PJM-AG1-090 is a proposed 95 MW hybrid solar and battery project located in Centre County, Pennsylvania. The project consists of 95 MW of solar generation. It is interconnected within the PJM Interconnection queue as of August 1, 2020, with a proposed commercial operation date of August 1, 2023. The project's interconnection status is currently in the Feasibility Study phase, and the point of interconnection is Philipsburg 115 kV.
The proposed project is located within the PENELEC utility service area.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
PA
County
Centre
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
CE-Black Moshannon OZ LLC
Utility
PENELEC
Entity
PJM
Service Type
NRIS
Point of Interconnection
Philipsburg 115 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- PHILIPSB115 KV UNSH_SP
- POI Substation
- Philipsburg Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Black Moshannon SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.