Waller Solar I
45 MW generation in Lancaster, VA · In queue since June 2020 · Proposed COD December 2027
45 MW
Capacity
1
Components
Solar
5y 11m
In Queue
IA Executed
IA Phase
COD target: 2027
Total Duration
7y 6m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-12-31
The proposed project PJM-AG1-038 is a 45 MW solar generation project located in Lancaster County, Virginia. The project is being developed within the Dominion service territory and has an interconnection queue entry date of June 16, 2020, in the PJM Interconnection queue. Its proposed commercial operation date is December 31, 2027.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Garner DP-Lancaster 115 kV substation. The project has appeared in recent news coverage regarding renewable energy development in the PJM region.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
VA
County
Lancaster
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
NRIS
Point of Interconnection
Garner DP-Lancaster 115 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Waller Solar IForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.