Harvey Solar I
127.5 MW generation in Licking, OH · In queue since June 2020 · Proposed COD January 2029
127.5 MW
Capacity
1
Components
Solar
6y 1m
In Queue
IA Executed
IA Phase
COD target: 2029
Total Duration
8y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2029-01-15
Interconnection Agreement executed per LBNL queue status
Harvey Solar I is a proposed 127.5 MW solar generation project located in Licking County, Ohio. The project is being developed within the PJM Interconnection queue as project AG1-034. The queue entry date is June 12, 2020, with a proposed commercial operation date of January 15, 2029. The interconnection status is currently in the Facility Study phase.
The project is interconnected to the AEP utility grid at the Centerburg 138 kV point of interconnection. The project has appeared in recent news coverage regarding renewable energy development in Ohio.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OH
County
Licking
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
NRIS
Point of Interconnection
Centerburg 138 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Harvey Solar IForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.