Deep Lake Solar
150 MW generation in Nicholas, WV · In queue since March 2020 · Proposed COD February 2029
150 MW
Capacity
1
Components
Solar
6y 8m
In Queue
IA Executed
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8y 11m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Engineering and Procurement
Project under construction
Typical: 12–24 months
Proposed COD: 2029-02-28
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 25, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed per LBNL queue status
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of February 2029. No independent news or press releases found to validate or contradict this date.
Developer: LBNL snapshot lists developer as null, and no news articles, press releases, or corporate announcements were found identifying the project sponsor or operating company.
Status: LBNL reports IA Executed status with active queue position. Absence of news coverage suggests project is in early development with no recent public milestones.
About
Generated Apr 10, 2026 · Predates Oct 25, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Deep Lake Solar is a proposed 150 MW solar generation project located in Nicholas County, West Virginia. The project is in the PJM interconnection queue as entry PJM-AF2-316, with a queue entry date of March 30, 2020, and a proposed commercial operation date of February 28, 2029. The interconnection agreement for the project has been executed.
The project, which interconnects at the Gilboa-Jones Branch 138 kV II substation, is being developed within the APS utility territory. Recent news coverage has discussed the project.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM queue source as of: Oct 25, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WV
County
Nicholas
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
NRIS
Point of Interconnection
Gilboa-Jones Branch 138 kV II
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- POI Substation
- Branch
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Deep Lake SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.