Union Ridge Solar
107.7 MW generation in Licking, OH · In queue since February 2020 · Proposed COD January 2026
107.7 MW
Capacity
1
Components
Solar
6y 5m
In Queue
IA Executed
IA Phase
Signed Aug 2021
Queue → IA
1y 6m
IA → COD
4y 5m
Total Duration
1y 6m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-01-31
Union Ridge Solar is a proposed solar generation project with a total capacity of 107.7 MW, located in Licking County, Ohio. The project is in the PJM interconnection queue as entry PJM-AF2-122, with a queue entry date of February 29, 2020, and a proposed commercial operation date of January 31, 2026. The interconnection agreement (IA) has been executed. The interconnecting utility is AEP.
The Union Ridge Solar project has been the subject of recent news coverage, with six articles appearing in industry, deals, and regulatory publications.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OH
County
Licking
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
NRIS
Point of Interconnection
Kirk 138 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- KIRK 34.5 KV UNIONRSP
- POI Substation
- Kirk Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all 5 articlesNo Ask reports yet for this entity.
Ask about Union Ridge SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.