Union Ridge Solar
107.7 MW generation in Licking, OH · In queue since February 2020 · Proposed COD January 2026
107.7 MW
Capacity
1
Components
Solar
6y 9m
In Queue
IA Executed
IA Phase
Signed Aug 2021
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 6m
IA → COD
4y 5m
Total Duration
1y 6m
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Partially in Service - Under Construction
Project under construction
Typical: 12–24 months
Proposed COD: 2026-01-31
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 25, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed with PJM
lbnl_queue_snapshotRWE begins construction with MasTec Renewables as EPC contractor
solarpowerworldonline.comResearch sources and reasoning (4 recorded sources)
high confidence at research time
- solarpowerworldonline.com/2025/05/rwe-begins-construction-on-nearly-100-mw-ohio-solar-project/
- prnewswire.com/news-releases/rwe-breaks-ground-on-second-solar-farm-in-ohio-creating-jobs-and-economic-opportunities-in-licking-county-302453954.html
- 10tv.com/article/news/local/550-acre-licking-county-solar-project-expected-finish-by-early-2026/530-4b5702cb-64ea-4f1f-a1fb-650d82bd24f0
- newarkadvocate.com/story/news/2022/01/28/union-ridge-solar-project-approved-state-but-construction-delayed/9226619002/
Commercial operation date: LBNL proposed COD of January 2026 aligns with news reports stating project expected to finish by early 2026. Construction began May 2025 per Solar Power World, supporting an early 2026 completion timeline.
Developer: LBNL queue snapshot has null developer field. News sources consistently identify RWE as the developer across 3 articles with 0.7-0.95 confidence. No shell LLC entity identified in available sources.
Status: LBNL shows 'active' with IA executed August 2021. News confirms construction started May 13, 2025 per Solar Power World and PR Newswire, with MasTec Renewables as EPC contractor.
About
Generated Apr 10, 2026 · Predates Oct 25, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Union Ridge Solar is a proposed solar generation project with a total capacity of 107.7 MW, located in Licking County, Ohio. The project is in the PJM interconnection queue as entry PJM-AF2-122, with a queue entry date of February 29, 2020, and a proposed commercial operation date of January 31, 2026. The interconnection agreement (IA) has been executed. The interconnecting utility is AEP.
The Union Ridge Solar project has been the subject of recent news coverage, with six articles appearing in industry, deals, and regulatory publications.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM queue source as of: Oct 25, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OH
County
Licking
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
NRIS
Point of Interconnection
Kirk 138 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- KIRK 34.5 KV UNIONRSP
- POI Substation
- Kirk Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all 5 articlesForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.