Union Ridge Solar (PJM-AF2-122) — Project Summary

Queue ID
PJM-AF2-122
Capacity
107.7 MW
Technology
Solar
Status
active
Location
Licking, OH
Region
PJM
Developer
IA Status
IA Executed

Union Ridge Solar

PJM-AF2-122BetaActiveSolarPJMLBNL + Live

107.7 MW generation in Licking, OH · In queue since February 2020 · Proposed COD January 2026

BA: PJMISO/RTO: PJMNERC: RFCRC: PJM

107.7 MW

Capacity

1

Components

Solar

6y 5m

In Queue

IA Executed

IA Phase

Signed Aug 2021

Status
Latest milestoneconstruction start · 2025-05-13Solar Power World · 2025-05-13
Interconnection

Queue → IA

1y 6m

IA → COD

4y 5m

Total Duration

1y 6m

Schedule

5 months past proposed COD

Construction75%
Queue EntryFeb 29, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection AgreementAug 8, 2021

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-01-31

Cross-source intelligence
Beta
High confidence·4 sources·as of 2026-06-01
Expected COD
Jan 2026
From queue filing
Developer
RWE
From queue filing
Status
Construction
Construction — groundbreaking occurred May 2025, MasTec Renewables as EPC contractor, targeting early 2026 completion
Financing
Secured
Financing secured (construction underway as of May 2025), specific terms not publicly disclosed
Key milestones
IA executedAug 8, 2021

Interconnection Agreement executed with PJM

source
Permit approvedJan 2022

Ohio Power Siting Board approved project

source
GroundbreakingMay 13, 2025

RWE begins construction with MasTec Renewables as EPC contractor

source
COD targetJan 2026Most recent

Project expected to finish by early 2026

source
Project lifecycle
as of 2025-05-13
PhaseConstructionThe Newark Advocate · 2022-01-28
OperationalNoPR Newswire · 2025-05-13
TechnologySolarPR Newswire · 2025-05-13
DeveloperRWE±PR Newswire · 2025-05-13
PPA offtakerAmazonThe Newark Advocate · 2022-01-28
EPC contractorMasTec RenewablesPR Newswire · 2025-05-13
GroundbreakingAnnouncedPR Newswire · 2025-05-13
Permit decisionGrantedThe Newark Advocate · 2022-01-28
About

Union Ridge Solar is a proposed solar generation project with a total capacity of 107.7 MW, located in Licking County, Ohio. The project is in the PJM interconnection queue as entry PJM-AF2-122, with a queue entry date of February 29, 2020, and a proposed commercial operation date of January 31, 2026. The interconnection agreement (IA) has been executed. The interconnecting utility is AEP.

The Union Ridge Solar project has been the subject of recent news coverage, with six articles appearing in industry, deals, and regulatory publications.

Generated from interconnection queue and public data sources

Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

OH

County

Licking

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

AEP

Entity

PJM

Service Type

NRIS

Point of Interconnection

Kirk 138 kV

Data Source

LBNL + Live

DeveloperRWE10TV · 2025-10-21
EPC contractorMasTec RenewablesSolar Power World · 2025-05-13
ApplicantUnion Ridge Solar±The Newark Advocate · 2022-01-28
AgencyOhio Power Siting BoardThe Newark Advocate · 2022-01-28
RulingApproval±The Newark Advocate · 2022-01-28
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
PJM
Trading Hub
AEP-DAYTON HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
KIRK 34.5 KV UNIONRSP
POI Substation
Kirk Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (5)Beta

Last updated 2026-03-26

View all 5 articles

No Ask reports yet for this entity.

Ask about Union Ridge Solar
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.