Union Ridge Solar (PJM-AF2-122) — Project Summary

Queue ID
PJM-AF2-122
Capacity
107.7 MW
Technology
Solar
Status
active
Location
Licking, OH
Region
PJM
Developer
—
IA Status
IA Executed

Union Ridge Solar

PJM-AF2-122BetaActiveSolarPJMLBNL + Live

107.7 MW generation in Licking, OH · In queue since February 2020 · Proposed COD January 2026

BA: PJMISO/RTO: PJMNERC: RFCRC: PJM

107.7 MW

Capacity

1

Components

Solar

6y 9m

In Queue

IA Executed

IA Phase

Signed Aug 2021

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1y 6m

IA → COD

4y 5m

Total Duration

1y 6m

Schedule

10 months past proposed COD

Construction75%
Queue EntryFeb 29, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection AgreementAug 8, 2021

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Partially in Service - Under Construction

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-01-31

News-reported activity
as of 18 months ago

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest milestoneconstruction startSolar Power World · 2025-05-13

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 25, 2026 queue source. See the queue record for reported project facts.

Research COD
Jan 2026
From queue filing
Developer in saved assessment
RWE
From queue filing
Status at research time
Construction
Construction — groundbreaking occurred May 2025, MasTec Renewables as EPC contractor, targeting early 2026 completion
Financing
Secured
Financing secured (construction underway as of May 2025), specific terms not publicly disclosed

Milestones in this assessment

IA executedAug 8, 2021

Interconnection Agreement executed with PJM

lbnl_queue_snapshot
Permit approvedJan 2022

Ohio Power Siting Board approved project

newarkadvocate.com
GroundbreakingMay 13, 2025

RWE begins construction with MasTec Renewables as EPC contractor

solarpowerworldonline.com
COD targetJan 2026Latest in this assessment

Project expected to finish by early 2026

10tv.com
Research sources and reasoning (4 recorded sources)

high confidence at research time

  1. solarpowerworldonline.com/2025/05/rwe-begins-construction-on-nearly-100-mw-ohio-solar-project/
  2. prnewswire.com/news-releases/rwe-breaks-ground-on-second-solar-farm-in-ohio-creating-jobs-and-economic-opportunities-in-licking-county-302453954.html
  3. 10tv.com/article/news/local/550-acre-licking-county-solar-project-expected-finish-by-early-2026/530-4b5702cb-64ea-4f1f-a1fb-650d82bd24f0
  4. newarkadvocate.com/story/news/2022/01/28/union-ridge-solar-project-approved-state-but-construction-delayed/9226619002/

Commercial operation date: LBNL proposed COD of January 2026 aligns with news reports stating project expected to finish by early 2026. Construction began May 2025 per Solar Power World, supporting an early 2026 completion timeline.

Developer: LBNL queue snapshot has null developer field. News sources consistently identify RWE as the developer across 3 articles with 0.7-0.95 confidence. No shell LLC entity identified in available sources.

Status: LBNL shows 'active' with IA executed August 2021. News confirms construction started May 13, 2025 per Solar Power World and PR Newswire, with MasTec Renewables as EPC contractor.

Project lifecycle
as of 2022-01-28
PhaseConstructionThe Newark Advocate · 2022-01-28
OperationalNoThe Newark Advocate · 2022-01-28
TechnologySolarThe Newark Advocate · 2022-01-28
DeveloperLeeward Renewable EnergyThe Newark Advocate · 2022-01-28
PPA offtakerAmazonThe Newark Advocate · 2022-01-28
DelayAnnouncedThe Newark Advocate · 2022-01-28
Permit decisionGrantedThe Newark Advocate · 2022-01-28

About

Saved background

Generated Apr 10, 2026 · Predates Oct 25, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Union Ridge Solar is a proposed solar generation project with a total capacity of 107.7 MW, located in Licking County, Ohio. The project is in the PJM interconnection queue as entry PJM-AF2-122, with a queue entry date of February 29, 2020, and a proposed commercial operation date of January 31, 2026. The interconnection agreement (IA) has been executed. The interconnecting utility is AEP.

The Union Ridge Solar project has been the subject of recent news coverage, with six articles appearing in industry, deals, and regulatory publications.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • PJM queue source as of: Oct 25, 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

OH

County

Licking

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

—

Utility

AEP

Entity

PJM

Service Type

NRIS

Point of Interconnection

Kirk 138 kV

Data Source

LBNL + Live

DeveloperRWE10TV · 2025-10-21
EPC contractorMasTec RenewablesSolar Power World · 2025-05-13
ApplicantUnion Ridge Solar±The Newark Advocate · 2022-01-28
AgencyOhio Power Siting BoardThe Newark Advocate · 2022-01-28
RulingApproval±The Newark Advocate · 2022-01-28
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
PJM
Trading Hub
AEP-DAYTON HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
KIRK 34.5 KV UNIONRSP
POI Substation
Kirk Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (5)Beta

Last updated 2026-03-26

View all 5 articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.