Project PJM-AF2-088 — Project Summary

Queue ID
PJM-AF2-088
Capacity
6.5 MW
Technology
Solar
Status
active
Location
Clearfield, PA
Region
PJM
Developer
IA Status
IA Executed

PJM-AF2-088

PJM-AF2-088BetaActiveSolarPJMLBNL + Live

6.5 MW generation in Clearfield, PA · In queue since February 2020 · Proposed COD September 2026

BA: PJMISO/RTO: PJMNERC: RFCRC: PJM

6.5 MW

Capacity

1

Components

Solar

6y 5m

In Queue

IA Executed

IA Phase

COD target: 2026

Interconnection

Total Duration

6y 7m

Construction75%
Queue EntryFeb 5, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-09-01

About

PJM-AF2-088 is a proposed solar generation project with a total capacity of 6.5 MW. The project is located in Clearfield County, Pennsylvania, within the PJM Interconnection region. The project, interconnecting to PENELEC, entered the PJM queue on February 5, 2020, and has a proposed commercial operation date of September 1, 2026. Its interconnection status is currently in the System Impact Study phase.

The proposed point of interconnection (POI) is the Shawville-Clearfield 34.5 kV II substation. The project consists of 6.5 MW of solar photovoltaic generation. The developer is not specified in the queue data, and there is no indication of an existing operating plant match or recent news coverage.

Generated from interconnection queue and public data sources

Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

PA

County

Clearfield

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

PENELEC

Entity

PJM

Service Type

NRIS

Point of Interconnection

Shawville-Clearfield 34.5 kV II

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
PJM
Trading Hub
WESTERN HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about Project PJM-AF2-088
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.