Gemstone Solar
150 MW generation in Cass, MI · In queue since January 2020 · Proposed COD December 2028
150 MW
Capacity
1
Components
Solar
6y 10m
In Queue
IA Executed
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8y 11m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Under Construction
Project under construction
Typical: 12–24 months
Proposed COD: 2028-12-31
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 25, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed per LBNL queue status
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of 2028-12-31. No independent news or press releases found to validate or update this target date.
Developer: LBNL snapshot contains no developer information, and live search yielded no results identifying the project sponsor or operating company.
Status: LBNL reports 'active' status with IA Executed. No contradicting information or construction announcements found in available sources.
About
Generated Apr 10, 2026 · Predates Oct 25, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Gemstone Solar project is a proposed 150 MW solar generation project located in Cass County, Michigan. The project is interconnected within the PJM Interconnection queue as entry PJM-AF2-083, with a queue entry date of January 31, 2020, and a proposed commercial operation date of December 31, 2028. The designated point of interconnection is Kenzie Creek-Stone Lake 69 kV, and the interconnection agreement has been executed.
The project is linked to the existing Gemstone Solar LLC operating plant (EIA plant ID 68061). The queue project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM queue source as of: Oct 25, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MI
County
Cass
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
NRIS
Point of Interconnection
Kenzie Creek-Stone Lake 69 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MUDDLAKE34.5 KV GEMSTNSP
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Michigan in Michigan growth signals — PPAs, construction, new projects
Summary analysis with parallel narrative sections and visualizations.
Michigan Wind 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Sky High Solar
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
What's the status of the 1 queue project linked to Gemstone Solar LLC?
Data-driven briefing on Gemstone Solar — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.