Rosegold Solar
150 MW generation in Blackford, IN · In queue since January 2020 · Proposed COD March 2030
150 MW
Capacity
1
Components
Solar
6y 10m
In Queue
System Impact Study
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
10y 2m
Study Phase
TC1
Interconnection request submitted to ISO/RTO
EP; FINAL AGREEMENT; TC1
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-03-31
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 23, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Original proposed COD per LBNL queue filing
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of October 2022. No independent news or research sources found to validate or update this date, which is now 2+ years past.
Developer: LBNL filing entity is 'Leeward Renewable Energy Development, LLC' which is the development subsidiary. Parent operating company is Leeward Renewable Energy (formerly Leeward Renewables, owned by OMERS Infrastructure).
Status: LBNL shows 'active' status in System Impact Study phase. However, the 2022 proposed COD has passed without any discoverable news of construction, financing, or progress, suggesting project may be stalled or delayed.
About
Generated Apr 10, 2026 · Predates Oct 23, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
PJM-AF2-068 is a proposed solar generation project with a total capacity of 150 MW, located in Blackford County, Indiana. The project is interconnected within the PJM Interconnection queue, having entered the queue on January 30, 2020. The proposed commercial operation date is October 3, 2022. The project's interconnection status is currently in the System Impact Study phase.
The proposed project, which is being developed within the AEP utility territory, consists of 150 MW of solar photovoltaic generation. The point of interconnection (POI) is the Jay 138 kV substation.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM_CYCLE queue source as of: Oct 23, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IN
County
Blackford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Leeward Renewable Energy Development, LLC
Utility
AEP
Entity
PJM
Service Type
NRIS
Point of Interconnection
Jay 138 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- JAY 138 KV T3
- POI Substation
- AEP Jay Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.