Scout Storage I
9 MW storage in Accomack, VA · In queue since January 2020 · Proposed COD April 2026
9 MW
Capacity
1
Components
Battery
6y 6m
In Queue
IA Executed
IA Phase
COD target: 2026
Total Duration
6y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 6–18 months
Proposed COD: 2026-04-01
The proposed Scout Storage I project is a 9 MW battery storage development in Accomack County, Virginia. It is located within the PJM Interconnection region and is interconnected with Delmarva Power & Light (DPL) at the Wattsville 12 kV point of interconnection.
The project, identified as PJM-AF2-060 in the PJM queue, entered the queue on January 25, 2020, and has a proposed commercial operation date of April 1, 2026. Its interconnection status is currently in the System Impact Study phase, but is currently listed as suspended.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
VA
County
Accomack
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DPL
Entity
PJM
Service Type
NRIS
Point of Interconnection
Wattsville 12 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- WATTSVIL69 KV LOADT1
- POI Substation
- Wattsville Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Scout Storage IForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.