Ontelaunee Power Generating Plant
20 MW storage in Berks, PA · In queue since October 2019 · Proposed COD March 2029
20 MW
Capacity
1
Components
Battery
6y 7m
In Queue
IA Executed
IA Status
COD target: 2029
Total Duration
9y 5m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2029-03-01
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
The proposed Ontelaunee Power Generating Plant is a 20 MW battery storage project located in Berks County, Pennsylvania. The project is in the PJM interconnection queue as entry PJM-AF2-030, with a queue entry date of October 28, 2019, and a proposed commercial operation date of March 1, 2029. The interconnection agreement for the project has been executed.
The project, which consists of 20 MW of battery capacity, is linked to the existing Ontelaunee 230 kV point of interconnection. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
PA
County
Berks
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ME
Entity
PJM
Service Type
—
Point of Interconnection
Ontelaunee 230 kV
Data Source
LBNL + Live
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ONTELAUN18 KV CT1
- POI Substation
- Ontelaunee Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Ontelaunee Power Generating PlantForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.