Zion Energy Center - BESS
50 MW storage in Lake, IL · In queue since November 2019 · Proposed COD July 2029
50 MW
Capacity
1
Components
Battery
6y 8m
In Queue
IA Executed
IA Phase
COD target: 2029
Total Duration
9y 8m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2029-07-02
The Zion Energy Center - BESS is a proposed 50 MW battery storage project located in Lake County, Illinois. Interconnecting to the ComEd utility, the project is in the PJM interconnection queue as entry PJM-AF2-027, with a queue entry date of November 15, 2019. The proposed commercial operation date is August 25, 2027, and the interconnection agreement has been executed.
The project, developed within the PJM region, consists of 50 MW of battery storage capacity. The point of interconnection is the Zion Energy Center 345 kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Lake
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
NRIS
Point of Interconnection
Zion Energy Center 345 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- 937 LEE 13.5 KV LEE31-1
- POI Substation
- Lee County Energy Center Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Zion Energy Center - BESSForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.