33 MW generation in Lorain, OH · In queue since October 2019 · Proposed COD June 2031
33 MW
Capacity
1
Components
Gas
6y 9m
In Queue
IA Executed
IA Phase
COD target: 2031
Total Duration
11y 8m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2031-06-01
The West Lorain Power Plant 345 kV project is a proposed 33 MW gas-fired generation project located in Lorain County, Ohio. The project is being developed within the PJM Interconnection queue under queue ID PJM-AF2-004. The project entered the queue on October 1, 2019, and has a proposed commercial operation date of June 1, 2031. The interconnection agreement for the project has been executed.
The proposed project will interconnect to the ATSI utility grid at the Beaver 345 kV point of interconnection.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OH
County
Lorain
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
NRIS
Point of Interconnection
Beaver 345 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- BEAV DUQ22 KV UNIT2
- POI Substation
- Beaver Valley Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about West Lorain Power Plant 345 kVForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.